Black Avenue Stormwater Improvements Project
This summer, the City of Bozeman will continue upgrades to the century-old storm drain system in the downtown area. The existing infrastructure along Black Avenue is significantly undersized and deteriorated, requiring full replacement.
Project Details:
The City has contracted CK May Excavating to remove and replace storm drain and sewer infrastructure along Black Avenue, from Main Street to Babcock Street.
Construction Schedule (estimated, dates and times can vary):
Travel Impacts:
Week of 7/14
- S Black Ave will be closed from Babcock St to Curtiss St, Babcock intersection will be open to east/west travel.
- S Black partially closed from Main St to Babcock St.
- The contractor will be replacing the crosswalk across Black Avenue at the Main Street intersection. Black Avenue will be closed at the Main Street intersection starting Thursday until early next week. Black Avenue will be open from Babcock to the alley between Babcock and Main. Main Street will remain open.
Planned Work:
Week of 7/11
- Pave Babcock St intersection and continue sewer main installation south toward Olive St.
Week of 7/14:
- Continue sewer installation up to Olive St and start sewer installation between Olive St and Curtiss St.
Important Notes:
- Access to local businesses will be maintained throughout the project.
- Sidewalk access will remain open but may be limited in certain areas for pedestrian safety.
Project Contacts:
- CK May Excavating: 406-388-0015, info@ckmayexcavating.com
- City of Bozeman – Karl Johnson: 406-451-1693, kajohnson@bozeman.net
Stay informed by checking weekly Road Reports for the latest project updates.